Energy Solution Using Indigenous Resources in Villages (Samundari, Veharri):

Samundari :
PV Modules : HTSAEE 330 Wp Polycrystalline
Inverter : Grid Interactive Inverter Baykee 150 KW
Bio Gas Generation: 150KW
Battery Bank : 85KWh
Grid/Gen Set Input : 440 Vac - 50 Hz

Veharri :
PV Modules : HTSAEE 330 Wp Polycrystalline
Inverter : Grid Interactive Inverter Baykee 300 KW
Bio Gas Generation: 100 KW
Battery Bank : 170KWh
Grid/Gen Set Input : 440 Vac - 50 Hz

The Energy Department of the Punjab (“Employer”) is developing two model projects for reliable and environmental-friendly electricity supply for rural areas in Punjab. The two PV Biogas Hybrid Systems, located in central and southern Punjab respectively, consist each of a PV part (photovoltaic power plant, “PV System”), a biogas energy part (biogas power plant including all necessary components, “Biogas System”), battery storage (“Battery”), grid connection incl. grid breakers, a control system and all necessary periphery. The PV Biogas Hybrid System shall provide the connected households a reliable electricity and (partially) gas supply around the clock and throughout the year, thus minimizing fuel and combustible expenses requiring foreign exchange and creating economic stimulus. Each PV Biogas Hybrid System shall generate electricity based on the two underlying renewable energies (solar irradiation and biogas). Both systems shall be connected to the electricity grid but shall also operate in off-grid mode when the electricity grid will not be available. Electricity produced shall primarily be used for supplying households in the village where the PV Biogas Hybrid System. At both sites 400 KW integrated energy plants are being installed by Dynamic Green and the organization is proving out to be the pioneers in executing and implementing the integrated renewable energy theory and concept.
Samundari Site :

Veharri Site :